Analysis of interacting uncertainties in on-site and off-site activities: Implications for hybrid construction

journal contribution
posted on 2024-11-02, 01:02 authored by Mehrdad Arashpour, Ronald WakefieldRonald Wakefield, Eric Lee, Ricky ChanRicky Chan, M. Hosseini
Interaction and integration of uncertainties in on-site and off-site project activities often result in the risk of delays and schedule overruns in hybrid construction projects. To address this problem, a holistic risk analysis approach that assesses the integrating impact of uncertainties on completion times is proposed. The results of the analysis show that growth in project size and work quantities intensifies pair and group interconnection of tasks within and between groups of on-site and off-site activities, resulting in lengthened completion times and deviations from project plans. Unavailability of resources, risk seeking attitudes, and workflow variability are other major contributors to the risk of late completion in hybrid construction. While project managers often analyze on-site and off-site uncertainties separately, practical implications of the research results suggest adoption of a holistic approach in which risk management practices in the two environments are integrated. This approach significantly improves tangible performance measures in projects.

History

Related Materials

  1. 1.
    DOI - Is published in 10.1016/j.ijproman.2016.02.004
  2. 2.
    ISSN - Is published in 02637863

Journal

International Journal of Project Management

Volume

34

Start page

1393

End page

1402

Total pages

10

Publisher

Elsevier

Place published

United Kingdom

Language

English

Copyright

© 2016 Elsevier

Former Identifier

2006062234

Esploro creation date

2020-06-22

Fedora creation date

2016-06-02